When plans shift, like a rain day or a crew swap, you don't have to open every piece of work. Tick it in the List view and change it all together.
Click List at the top of the schedule.
Tick the box next to each piece of work you want to change. Tick the box in the header to select everything on the page.
In the Edit Tasks panel, pick what to change: Update status, Edit starts, Edit due, Edit labels or Edit assignees.
Set the new value and apply it.
Note: What you set replaces what's already there. For example, editing assignees puts the same crew on everything you ticked.
Tip: Use Search or a filter first to narrow the List to the work you want, like one crew's work this week.
Or let Ask Workyard do it: say what changed, like “Push all of Parker's crew's jobs on Monday back one day”, then check the changes before you apply them. See Plan your schedule with Ask Workyard.
Change several pieces of work at once
Change lots of work from the Workyard mobile app
Admins and managers can mark lots of work complete or incomplete at once from the Workyard mobile app:
Open Tasks and tap List.
Tick the box next to each piece of work you want to change, or tap Select all.
Tap Bulk actions, then Mark as complete or Mark as incomplete.
To change dates, labels or crew on lots of work at once, use the List on the web.
Tick the work on the List tab, then tap Bulk actions to mark it complete or incomplete